Hills Mayor, Dr Peter Gangemi, has reported on the latest update on Kenthurst Park.
The Kenthurst Park project includes increasing the size of the southern sports field area to accommodate two full-sized playing fields and enhancement of the existing cricket oval.
The work requires significant earthworks and retaining wall construction and includes a new irrigation system, sports field LED lighting and stormwater drainage of the two sports fields and new gardeners and sports storage sheds. All earthworks, retaining wall construction, stormwater drainage, electrical pre-work and installation of the lighting towers are now complete.
Current works in progress include:
Preparation of playing field construction for turfing
Irrigation system installation
Construction of the sheds
Bushland regeneration work